Quality Checks in Manufacturing

Choose the inspection point​

OperationCheck and locationPending blocking check prevents
Work OrderOperation output, on the work order and in Shop FloorReport Production
Finished Goods ReceiptFinished item, on the manufacturing orderReceive Finished Goods

The manufacturing order shows the finished goods check. Approval creates work orders from operations already in the bill of materials. An operation added afterward requires a new order to become a work order.

Run checks during production​

  1. Set up the tracked product, component stock, production warehouse, work center and bill of materials with an operation.
  2. Create matching quality points, such as a blocking work-order point for Assembly and a blocking finished-goods point for the product.
  3. Create and approve the order. Open the work order from Operations, start it, complete the check and report production. Attempting to report with a pending blocking check shows the check number.
  4. Consume components, complete the finished goods check, receive the output and complete manufacturing.

Checks are generated on first opening the source. If you add a point later, refresh the source to check for a match. Points for Manufacturing do not trigger in companies without Manufacturing installed.

Enter results in Shop Floor​

Open the work order in Shop Floor. The Quality Check section above Instructions shows the number, product and status. Enter a measurement, pass or fail result, or instruction acknowledgment. For photo steps, use Open Check Screen to add the attachment. Select Save Check and review the result. After completion the section displays the recorded result.

A pending blocking check shows a dialog instead of production reporting. Cancel returns to the job and Go to Check scrolls to its check section. Viewing requires Quality view permission. Entry requires permission to perform checks.

Schedule inspection as its own operation​

Create a Quality Control work center and a Final Inspection operation after Assembly in the bill. Define a work-order quality point matching that center. Approval creates a separate job in its queue, and scheduling includes its center time and capacity. A point for that center can apply to other operations or bills that use it.

Handle a failed check​

An Internal nonconformity opens. A failed work-order check has no stock to quarantine. A failed finished-goods check can quarantine each subsequent receipt, including partial quantities. See Quarantine and Disposition.