Task Stages and Tags

Configure company-wide stages​

Open Project Management → Configuration → Task Stages with configuration permission. Stages are shared by all projects in the active company.

Select New and enter Name, Order of zero or greater, and Count as Completed, then save. New stages start active. Open an existing stage to edit its Active setting. Names must be unique within the company regardless of case. Order defaults to 10 and determines the sequence of active columns.

Initial stages may include New, In Progress, On Hold, and Completed. Names can be changed. New tasks default to the lowest-ordered active stage. Check that it is open when starting work.

How a stage completes a task​

Saving or moving a task into a stage with Count as Completed enabled marks it complete and records the completion time. Moving it to an open stage reopens it and clears the completion time. A stage name alone does not set completion.

The setting cannot change for a stage used by an unarchived task. Stage configuration does not bulk recalculate tasks. Project status and milestone status are managed separately.

Deactivate a stage​

Clear Active and save to remove the stage from new selections and Kanban. Existing tasks keep their stage and remain available in List. Move open tasks to an active stage before deactivating it if they need to remain on the board. You can reactivate the stage and refresh Kanban. Use Order to arrange columns. There is no delete or drag-to-reorder action.

Configure task tags​

Open Configuration → Tags → New, enter Name, and save. Names are unique within the company regardless of case. New tags start active. Open a saved tag to change its name or active status.

In the task form, select any number of active company tags. Cards display tags, and List can filter by them. Projects have no tag field. Tags do not change priority, stage, assignment, duration, or financial records.

Deactivating a tag removes it from new selections while preserving existing links. Review the selections before resaving a task with an inactive tag, as the save can be rejected. Tags have no delete or color setting.

Verify the configuration​

Check name, order, closed status, and active status in Task Stages. Compare active Kanban columns with the stages shown in List. Check tag name and status in Tags, selection in the task form, and display on the card. Use the stage's open or closed setting to verify task completion.