Leave Duration and Workday Calculation
Start and end dates
Both dates are inclusive. For each date, Arvo checks the employee's applicable schedule and the company's default holiday calendar. Schedule priority is temporary schedule → shift rotation → regular schedule → no schedule. Rotation rest days are kept.
Leave is counted in day fractions without weighting by scheduled hours. Each requested half of a workday that is not a holiday counts as 0.5 days. Two such halves count as 1 day. Hourly entry is unavailable.
Weekends and half days
A Saturday or Sunday counts based on the schedule and holidays for that date. Half-day requests must cover one date, and the leave type must allow them. First Half Day and Second Half Day refer to the two halves of the workday. The request form does not take a time range.
| Schedule and holiday | Request | Calculated days |
|---|---|---|
| Workday, no holiday | Full day | 1 |
| Workday, no holiday | First or second half | 0.5 |
| Workday, morning holiday | Full day | 0.5 |
| Workday, morning holiday | First half | 0 |
| Nonworking day or full-day holiday | Full day | 0 |
A request is rejected if the entire period adds up to zero. For example, Friday through Monday counts as two days on a Monday-to-Friday schedule without holidays. A schedule with Saturday work can produce a different result.
Holiday calendar
Arvo uses full- and half-day entries in the active company's active default holiday calendar. If there is no calendar, it assumes no holidays. A working-day exception removes the holiday effect but does not turn an employee's scheduled day off into a workday by itself. Verify the holiday entries for your company.
The holiday calendar supplies duration inputs. The Time Off source in Calendar displays approved requests. Seeing a half-day request in the all-day area does not change the number of days counted.
When a schedule changes
Days are calculated when a request is created or a draft is updated. Submit and Approve use the saved value. If the schedule or holidays change, save the draft again and verify Calculated Days. Approved requests cannot be edited. Review previous attendance calculations separately.