Planning and Resource Utilization
Review the schedule
Use Manufacturing → Planning to filter work center load and work orders by date, center and status. Review overlaps and unscheduled jobs. Times use the company time zone.
Approval schedules forward from the later of planned start and current time. It considers prerequisites, work center calendars, unavailable time and occupancy by open work orders. A center schedules one job at a time. Capacity is output per cycle. Independent operations can be placed separately, subject to resource availability and copied alternative-center eligibility.
Read durations and replan
Expected duration is frozen for the nominal quantity. Schedulable duration covers remaining execution. A schedule window can span breaks, and actual work-center time comes from execution. Utilization is scheduled working time divided by available working time.
Replan changes only eligible open jobs that have never started. Started, paused and completed jobs retain their assignments and history. Paused work can still occupy the resource. Invalid resources, cancelled predecessors and insufficient available time can block scheduling. The target finish date is a planning target.
Compare order operations with the planning list. Check material readiness and physical production independently.