Skip to main content

Manufacturing Process

Prepare the order​

Use manufacturing to produce a stock-tracked item from components and receive the correct variant into inventory. Set up the product and variant, bill of materials, operations, work centers and calendars where applicable, and the manufacturing warehouse. Check the active company, permissions and Inventory integration for physical operations.

Work order start checks materials and dependencies. Starting work or reporting output records progress. Material consumption and finished goods receipt are separate physical actions. The order of consumption and reporting can vary. A bill of materials without operations produces no work orders. Use the manufacturing order for consumption and receipt in that case.

Plan and approve​

Create a manufacturing order with a product and variant, positive quantity, bill of materials, planned start and target finish. The draft preview reads the current bill of materials. Approval copies the applicable component, operation and by-product definitions to the order and creates work orders. The copied definitions are retained if the bill of materials later changes.

With Inventory integration enabled, approval reserves eligible available stock. A shortage can leave the order approved with incomplete reservations. Starting work requires sufficient reservations and applicable consumption or carry-over coverage. Use Prepare Materials to retry missing reservations. Component manufacturing orders are managed separately.

Execute and receive stock​

Run operations from Work Orders or the Shop Floor. Report the additional quantity produced in each operation. Use Consume to record the physical material issue. Allowed deviations from planned usage depend on the consumption policy copied at approval.

Use Receive Finished Goods to receive the quantity currently eligible into the manufacturing warehouse’s stock location. The planned quantity, applicable operations and consumption capacity limit receipt. Finished goods and eligible by-products are received together. Supply lot and serial details according to the receipt preview. See Finished Goods Receipts.

Complete the order or move the remainder​

Complete Production checks full receipt, required work completion and the consumption policy before closing the order. For partial receipts, use create an order for the remainder where eligible.

Record component loss and work-in-progress scrap through the appropriate correction. Review quantity and financial effects separately when an authorized physical correction is made against a completed order.

Verify production and accounting​

  1. Check planned, received and remaining quantities, component reservations and consumption, and reported work orders. Verify physical records in Stock Status, Movements and Manufacturing Traceability.
  2. Prepare valued raw material stock and the company’s manufacturing accounting cutover. Finished physical consumption can transfer value from raw material inventory to work in progress when the integration applies.
  3. Record work center time and reported output. Use recorded work center time for operation costs. Compare estimates, actual costs and allocated output value in the cost view.
  4. Receive the main product and by-products. After completion or eligible remainder closure, check for an unallocated difference. Prior valued issues of the same item can prevent automatic allocation.
  5. Follow the Accounting tab to journal entries, and review unposted events and WIP reconciliation in Manufacturing Accounting. Compare stock quantities, output values and ledger balances. Apply physical corrections and accounting reversals separately where required.

Normal component scrap enters the cost pool. Abnormal component scrap goes to a separate expense account. See Inventory and Manufacturing Accounting for posting, cutover and treatment of pre-cutover production.